Summit Construction Co.
DU
Estimates/Kitchen Remodel — Full Scope

Kitchen Remodel — Full Scope

Anderson Kitchen Remodel

accepted

01Demolition

2 items
DescriptionQtyUnitUnit CostTotal
Remove existing cabinets and countertops1ls$2,500.00$2,500.00
Remove flooring (250 sqft)250sqft$3.00$750.00
Subtotal$3,250.00

02Cabinets & Countertops

2 items
DescriptionQtyUnitUnit CostTotal
Custom shaker cabinets — supply & install1ls$18,000.00$18,000.00
Quartz countertops — 45 sqft45sqft$120.00$5,400.00
Subtotal$23,400.00

03Plumbing & Electrical

2 items
DescriptionQtyUnitUnit CostTotal
Plumbing rough-in and fixture install1ls$6,500.00$6,500.00
Electrical — new outlets and under-cabinet lighting1ls$4,200.00$4,200.00
Subtotal$10,700.00

04Flooring & Finishing

4 items
DescriptionQtyUnitUnit CostTotal
LVP flooring — supply & install250sqft$8.00$2,000.00
Tile backsplash30sqft$25.00$750.00
Paint — walls and trim1ls$3,400.00$3,400.00
Hardware and final cleanup1ls$4,000.00$4,000.00
Subtotal$10,150.00
ESTIMATE TOTAL$47,500.00